Last Thursday, the company came here to install our clean booth(three parts).
1. The first part is for in-air bench, it is high level clean.
2. The second part is for electronics and control.
3. The third one is for changing cllean suit.
After this installment, we cleaned everything would be put in and already in the room. We made also other changes.
1. We connected everything need to be connected. All the cables are gonging under the steps around the in-air bench.(Fig 1).
2. The Laser switch boxes are all under the in-air bench now.(Fig 2)
3. The control computer and transmission camera monitor are in the second part clean room now.(Fig 3)
Finally, we brought back the locking of our filter cavity both for green and infrared.