LOG-IN
Displaying reports 2441-2460 of 3274.Go to page Start 119 120 121 122 123 124 125 126 127 End
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 19:15, Tuesday 28 August 2018 (961)Get code to link to this report
3 beams profile

I measured the profile of the three beams. See the attached plot.

In order to match the waists with the crossing point, I have to move the focusing lens of the 1310nm probe forward by about 25mm, but there is no space.
To make space I'm thinking about adding a 90:10 BS (I have a spare) and change the optical path as shown in the draft design attached.

Images attached to this report
961_20180828121342_3beams.png 961_20180828121403_draftdesign.jpg
R&D (FilterCavity)
Print this report.
EleonoraCapocasa - 15:45, Tuesday 28 August 2018 (960)Get code to link to this report
Comment to Attempt to realign the cavity after TAMA blackout (Click here to view original report: 954)

Yesterday 27 Aug we made another try to move end mirror picomotors. We easily recovered the condition when the beam passing  through the hole of the second target was reflected by the end mirror on the back of the target, but displaced  few cm in yaw from the center. Unfortunately the yaw picomotor is still stuck and we could not recover the alignement. We are probabably left with no other option that opening the chamber.

R&D (FilterCavity)
Print this report.
YuhangZhao - 14:58, Tuesday 28 August 2018 (959)Get code to link to this report
Comment to The alignment of crystal with the p-pol and coherent control beam (Click here to view original report: 955)

Participants: Yuhang, Eleonora, Matteo

The transmission found before seems to come from a beam passing through a gap beside the crystal (it was too bright and the reflection was very small and with a strange shape)

 Therefore we have restarted the alignment from the beginning.  We moved the the 9071 newport Four-Axis Tilt Aligner under the OPO following the usual procedure:

1. Make the reflection superpose the incoming beam

2. Look for a good transmission, always taking care to keep the reflection superposed to the incoming beam.

After may tries we could find a resonably good shaped transmitted beam with a power of  0.047mW. The input power was 210mW. This means the reflectivity is 99.977%, which is in agreement with what we expect.

We put a dichroic mirror after the OPO. The reflection is focused on a photodiode while the trasmission is sent to a camera. Before installing the OPO we have marked the position of the transmitted beam on the screen in order to use it as a reference for the alignment.

Unfortunaltely  the tramission after the dichroic mirror is too low and we cannot see any light on the camera, therefore we were not able to use the reference we took for the transmitted beam.

R&D (FilterCavity)
Print this report.
MarcEisenmann - 22:38, Monday 27 August 2018 (958)Get code to link to this report
Comment to Green beam reflected by the FC (Click here to view original report: 935)

There were few mistakes made on this entry corrected in this one.

Attached to this entry is the proper fit of beam after the lens (previously a wrong wavelength was used for the plot).

The mean profile was used (w0 = 113.37 um 0.6981 m after the f = 100mm lens used for the characterization [lens is 40 cm after the Faraday Isolator])

 

The beam parameter is the following : w0 = 18.921 um @ 0.1168 m before the lens ie roughly 0.28320m after the faraday isolator.

Images attached to this comment
958_20180827152802_greenreflbeambyfc.png 958_20180827152807_meangreenrefl.png
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 21:51, Monday 27 August 2018 (957)Get code to link to this report
1310nm probe optical path assembled and aligned.

I assembled the components for the optical path of the 1310nm probe:

- Fiber collimator. Output mostly p-polarized.
- Polarizing PBS. Transmission: ~90mW, Reflection ~6mW. The reflection goes to a beam dump.
- Half-Wave Plate
- Polarizing PBS rotated  so that the reflection goes upward (to a high power beam dump) and the transmission is s-polarized
- Focusing lens f=300mm
- non-polarizing BS 90(R):10(T).
- Transmitted beam (10%):
     - Gold coated mirror
     - Converging lens f=50mm
     - PD DET10N mounted on a XY lens mount
- Reflected beam (90%)
     - Gold coated prism mirror.
     - To the crossing point...

Then I aligned the beam to impinge at 0.135rad on the sample at the crossing point. The pump is at 2deg (0.035rad) to avoid the etalon effect on the thin samples, this makes the angle between the 1310nm probe and the pump 0.1rad.

Images attached to this report
957_20180827145144_probe1310.jpg
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 19:06, Friday 24 August 2018 (956)Get code to link to this report
Imaging unit alignment, acoustic noise reduction, reference samples scan and tama-size Sapphire scan

- Aligned the imaging unit. Using a blade at about 1cm from the crossing point. I moved the lens on the imaging unit until I saw a sharp image of the blade at the detector position.

- Using the surface reference sample I aligned the pump with the probe to maximize the signal. Then I maximized the signal finely adjusting  the position of the whole imaging unit.

- I noticed that there was some noise (around 300uV in the AC signal) with a constant phase. It came from the chopper vibration. So I put some sound absorbing panels and the noise reduced to about 50uV.

- I made a scan of the bulk reference sample with a pump power of 32mW

- I made a scan of the tama-size sapphire and I got the same absorption as before changing the pump size. 

- Compared the scans of the bulk reference sample with small pump and large pump. They give the same value (unexpected) but they have a different shape. To be understood.

Images attached to this report
956_20180824115832_34.png 956_20180824115837_16.png 956_20180824115845_23.png 956_20180824120022_bulkrefpump80pump36.png 956_20180824120536_tama2pump80pump36.png 956_20180824120921_a1.jpg 956_20180824120926_a2.jpg 956_20180824120931_a3.jpg 956_20180824120934_a4.jpg 956_20180824120938_a5.jpg 956_20180824120941_a6.jpg
R&D (FilterCavity)
Print this report.
YuhangZhao - 17:44, Friday 24 August 2018 (955)Get code to link to this report
The alignment of crystal with the p-pol and coherent control beam

participaint: Yuhang and Matteo

After the pre-alignment of crystal, I did final algnment yesterday. The method is to move Newport 9071, vertically and herizontally. 

The experience is to move two of those four adjustment screws the OPO hole where the beam comes in. The requirement of this adjustment is to make the reflection beam overlap with incident beam. However, at the same time, pay attention that the whole OPO housing should be bascially looking like not tilt. Because we know the beam is bascially aligned pretty well.

During the alignment, I found the reflection looks like the attached figure 1(for the good alignment).

Then we can move the two another side sctews. At the same time, look at the transmission, at a certain point, we can see the trasmission is bright and looks round.

We still need to do aligment of the combination of two horizental screws to make it look better. While doing this, I found the beam is cutted by the crystal after move the incident tilt screw. This means the beam we are looking at is what we want to find. While moving the outgoing tilt screw, we can see the beam is cutted and then many small blocks of lights. This looks like many reflectivity of beam inside the crystal.

In the end, I got the transmission as in attached figure 2 and 3.

Images attached to this report
955_20180824104020_586805911.jpg 955_20180824104439_527782165.jpg 955_20180824104447_304903186.jpg
Comments related to this report
YuhangZhao - 14:58, Tuesday 28 August 2018 (959)

Participants: Yuhang, Eleonora, Matteo

The transmission found before seems to come from a beam passing through a gap beside the crystal (it was too bright and the reflection was very small and with a strange shape)

 Therefore we have restarted the alignment from the beginning.  We moved the the 9071 newport Four-Axis Tilt Aligner under the OPO following the usual procedure:

1. Make the reflection superpose the incoming beam

2. Look for a good transmission, always taking care to keep the reflection superposed to the incoming beam.

After may tries we could find a resonably good shaped transmitted beam with a power of  0.047mW. The input power was 210mW. This means the reflectivity is 99.977%, which is in agreement with what we expect.

We put a dichroic mirror after the OPO. The reflection is focused on a photodiode while the trasmission is sent to a camera. Before installing the OPO we have marked the position of the transmitted beam on the screen in order to use it as a reference for the alignment.

Unfortunaltely  the tramission after the dichroic mirror is too low and we cannot see any light on the camera, therefore we were not able to use the reference we took for the transmitted beam.

R&D (FilterCavity)
Print this report.
EleonoraCapocasa - 16:50, Thursday 23 August 2018 (954)Get code to link to this report
Attempt to realign the cavity after TAMA blackout

Participants:  Yuhang, Eleonora

We have tried to recover the cavity alignment after TAMA blackout.

1) We have reset all the local controls. For the input and end mirror we have reset the SR560 which filters the error signals (2nd order lowpass filter with cut-off frequency 100 Hz and amplification factor 100)

2) We observed that the reference out of BS chamber, accunting for PR position, was very far from the good position, especially in pitch. Since the local control range was too small, we used picomotors to recover it. Pic 2 shows the reference after moving PR.

3) We had to move also the BS picomotors to recover the good position of the beam on the two in vacuum targets and make the beam to reach the screen after the end mirror, used as a reference for the alignement.

4) At this point we aligned the input mirror in order to have the reflected beam superposed on the input beam.

5) The last step is to align the end mirror. The standard procedure, when no flashes are visible, consists in raising the second target and making the beam to pass through its hole. Than the end mirorr is aligned by making the reflected beam to hit the hole of the target from the back. The reflection can be observed by monitoring the rear side of the target.  Unfortunatly the range of the local control was not enough and the end mirror picomotor got stuck in yaw so we were not able to align the end mirror and to see any flash.  Pic 2 shows the rear side of the second target, with the reflected beam offset in yaw with respect to the hole of few cm.

SOME DETAIL ON END MIRROR PICOMOTOR: We used both the computer and the joystick to move it. Pitch was always fine. Yaw was moving at the beginning but after a while it got stuck. We tried to switch the driver on and off many times, to swap the channels but it didn't solve the problem.

Since we moved the end picomotor in pitch we observed a higher movement of the mirror with  typical peaks in the spectrum which are not normal mode of the suspension (see pic 3). It made me suspect that the intermediate mass is touching the frame of the damping magnets. We already observed something similar in PR suspension (see entry 239 and confront the spectra). 

Even if the damping loop is effective in reducing the mirror motion, this should be possibliy solved.

HOW TO GO ON: according to our experience, picomotors which are stuck are likey to start working again after a while. So we will try to move it again in the next days, before considering to open the chamber.

Images attached to this report
954_20180823094910_target.jpg 954_20180823094919_referencepr.jpg 954_20180826032223_end.png
Comments related to this report
EleonoraCapocasa - 15:45, Tuesday 28 August 2018 (960)

Yesterday 27 Aug we made another try to move end mirror picomotors. We easily recovered the condition when the beam passing  through the hole of the second target was reflected by the end mirror on the back of the target, but displaced  few cm in yaw from the center. Unfortunately the yaw picomotor is still stuck and we could not recover the alignement. We are probabably left with no other option that opening the chamber.

General (General)
Print this report.
MatteoLeonardi - 19:09, Wednesday 22 August 2018 (953)Get code to link to this report
Tunnel inspection
In this note I report about the inspection of the air conditioning system, lights and dehumidifier in the TAMA tunnels.

SOUTH tunnel:
- Dehumidifier: all ON, all green light
- Light: all working

SOUTH end:
- Air conditioning: working
- light: all working
- phone: working (3472)

WEST tunnel:
- Dehumidifier: all ON, 9/10 green light, N.5 (last from the central area before the mid-arm) is ON but red light.
- Light: all working, 3 fluorescent tube were substituted today.

WEST end:
- Air conditioning: NOT working (further inspection needed)
- light: all working
- phone: NOT working
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 20:40, Tuesday 21 August 2018 (951)Get code to link to this report
New design of pump beam and HeNe probe alignment
In order to make room for a mirror to deflect the reflection of the pump, I made a new design with Jammt. Now we use a 50mm lens and a 100mm lens. In this design, the beam size on the 100mm lens is larger, so the position of the waist is further. Since the waist has to stay in the same position as before (the usual position of the crossing point), we put backward the last lens, and this makes room for the mirror. The mirror sends the reflection to a high power beam dump outside the optical board.
Then I measured the pump beam profile. The waist is 36.4um and its position 38.4mm (in the translation stage reference)
 
To align the probe I used a mirror and a prism mirror. the probe has to be at 0.1rad from the incident pump. But the pump is already at 2deg = 0.035rad, so the probe angle has to be  0.1-0.035 = 0.065rad. I made the alignment with the usual pinhole making the beam pass through two positions of the pinhole (start and end):
           x 327.432mm
- center: y 121.255mm     z 34.9mm
- start   : y 121.255+20*0.065mm = 122.555mm   z 14.9mm 
- end    : y 122.555-100*0.065 = 116.055mm     z 114.9mm
 
After making sure that the probe beam is at the right angle, I put a converging lens. First I used the  300mm lens but the beam was too far from the crossing point position and too large. So I used a  250mm lens and measured the beam profile. The waist is 170um and its position 40.4mm (in the translation stage reference). Very close to the pump waist position. But more than 3times larger than the pump.
 
Now there could be a problem because the reflection of the pump passes very close to the probe prism mirror. The beam is quite large and only the tail of the spot touches the prism, but the power will be very high, so, I'm not sure if this will cause some thermal lens effect on the probe.
Images attached to this report
951_20180821105216_pumpproofile50mm100mm.png 951_20180821105226_probeprofile250mm.png 951_20180821105355_newpumpsize50mm100mm.png 951_20180821134022_whatsappimage201808211.jpg 951_20180821134026_whatsappimage201808212.jpg 951_20180821134030_whatsappimage201808213.jpg 951_20180821134035_whatsappimage201808214.jpg 951_20180821134039_whatsappimage201808215.jpg 951_20180821134044_whatsappimage201808216.jpg 951_20180821134049_whatsappimage201808217.jpg
R&D (FilterCavity)
Print this report.
YuhangZhao - 10:28, Tuesday 21 August 2018 (952)Get code to link to this report
The preparation work for OPO alignment

Participaint: Marc, Matteo and Yuhang

Since we have finished the lens installation for OPO, we arrived the alignment of OPO.

Last week, me and Marc did a similar work, including the preparation of periscope, camera, iris, OD filter and the alignment of the beam(make it hight of 140mm). However, the elevation of beam costs too much space. It makes the beam waist locate just after the periscope. After that we decide to alignment the OPO without the translation/tilt stage. However, the work seems impossible without that stage.

Yesterday, we changed the set of stage(make it hight of 111mm). This saves us a lot of space. We also did the beam measurement and find the beam is desirable.(as in the attached figure) We set up the periscope and did the pre-aligment of OPO. The pre-alignment is to make the reflection of OPO roughly overlap with incident beam. The fine-alignment will be done today by using translation/tilt stage. For the components after OPO, we set up a dichroic mirror instead of OD filter to damp the beam and also get the reflection information. For the transmission of dichroic, we use a camera to monitor. We also align it before putting OPO. And made a circle to mark it on the screen.(as in the attached figure). We also set up a photo diode for the reflection of dichroic mirror.

The video of check the reflection is here. https://drive.google.com/file/d/1-ZfhVS0iZDxF7kWpSCrn2QO5ORTTX4xU/view?usp=sharing

The whole set up is attached as well. 

Images attached to this report
952_20180821032751_2098149364.jpg 952_20180821032758_1362403394.jpg 952_20180821035403_20180820.png
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 21:39, Sunday 19 August 2018 (950)Get code to link to this report
Pump restored, aligned at 2deg and size reduced
There is no space on the breadboard to add the lenses to reduce the pump and to add the optics to control the polarization of the 1310nm probe.
Therefore I decided to put a larger breadboard and realign everything.
 
1. Removed the old breadboard and replaced it with a larger one. Since the new breadboard is thinner, to reach the same hight I had to add 4 1cm-thick spacers between the posts and the breadboard.
 
2. Placed back the periscope and aligned it to have the pump beam arriving at 2 degrees on the pinhole.
To do that I maximized the power transmitted by the pinhole in two positions at 2deg from the center (start and end). When the pinhole is at the start position I aligned moving the steering mirror on the optical table. When the pinhole was at the end position I  aligned moving the mirror on the periscope (usual procedure to align a beam to make it pass through two points).  
pinhole positions:
           x 327.432mm
- center: y 121.255mm     z 34.9mm
- start   : y 120.555mm     z 14.9mm
- end    : y 124.055mm     z 114.9mm
 
3. Added the lenses (f=100mm at 185mm from the pinhole, and f=-100mm at 125mm from the f=100mm lens) to converge the pump in the pinhole in the center position
 
4. Measured the Pump beam profile.
 
5. Tried to collect the reflected beam but noticed that it hits the mount of the 100mm lens. I can't risk to heat up the mount of the lens, but I don't have enough space to put some deflecting mirror between the lens and the edge of the breadboard. So I have to redesign the telescope to be able to move the last lens backwards and make some room for a deflecting mirror for the pump.
Images attached to this report
950_20180819143526_1.jpg 950_20180819143530_2.jpg 950_20180819143533_3.jpg 950_20180819143536_4.jpg 950_20180819143611_newpumpsize.png 950_20180819143945_newpump100100.png
R&D (FilterCavity)
Print this report.
MarcEisenmann - 10:11, Friday 17 August 2018 (949)Get code to link to this report
Air conditioning in end rooms

When we went to the end room with Takahashi-san, we saw that the south end room (the one we're currently using) was hot and humid.

The power was only off since one stormy day so it can't explain this.

It seems that every now and then the air conditioning system stop in both end rooms.

Seeing the damages in the west end room it could be useful to go from time to time to check if the air conditioning is on in both end rooms.

R&D (FilterCavity)
Print this report.
MarcEisenmann - 10:08, Friday 17 August 2018 (948)Get code to link to this report
CC and p-pol beams

We slightly moved the positions of the last lens of the OPO telescope as well as the one of the EOM.

We obtain the 2 characterizations attached to this entry.

The nominal value of the beam inside the OPO should be 36 um so we are now within +/- 1.3 um of the nominal value.

The OPO telescope was adjusted so to have the mean beam radius of 36 um.

The x-axis "0" is the last hole of the rail.

The 2 beams are still superposed as we could see on the beam profiler.

Images attached to this report
948_20180817030655_ccbeam.png 948_20180817030703_ppol.png
R&D (FilterCavity)
Print this report.
MatteoLeonardi - 16:01, Thursday 16 August 2018 (947)Get code to link to this report
Vacuum system recovery after the blackout
The vacuum system has been rebooted after the blackout of this Monday.
All the four pumping station are now back in operation and the vacuum level reached the 10^(-8) mbar level.
As a consequence of the blackout, all the three big gate valves along the arm were closed. After switching on the air compressor, the three gate valves opened.

Note: the penning at the South End station, tunnel side, measures 1.0e-7 TORR even if the other instrument (tower side) is deep in the 10^(-9) region. I tried to close the arm gate valve and the turbo pump gate valve on that side to check if the value was real or stuck and it seems that that penning cannot go lower than 1.0e-7 TORR.
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 19:57, Wednesday 15 August 2018 (946)Get code to link to this report
1310nm probe noise investigation: change polarization

The output fiber of the laser is single mode, polarization maintaining.

The reason of the jumps could be related to the polarization or some modes hops. So I tried to rotate the polarization.

Until now the polarization of the beam exiting the fiber was P (I didn't consider this parameter when I assembled it).

I rotated the fiber collimator in its mount by 90deg, in order to have S-polarization.

In this configuration, the loop works better. See the plot

Since rotating the collimator caused the misalignment, I ordered beam splitters and a half wave plate to optimize the polarization without loosing the alignment every time (they should arrive within one week.)

The out-of-loop PD was on the waist of the probe (at the sample position). The final test will be to put the out-of-loop PD on the imaging unit, where it will sense only the central part of the beam.
If the jumps we see in the intensity are related to the modes, and therefore to the shape of the beam, then the loop will not work, because the in-loop PD will see the total power, and doesn't see the shape.

Images attached to this report
946_20180815125710_20180815spolppol.png
R&D (FilterCavity)
Print this report.
MarcEisenmann - 19:02, Monday 13 August 2018 (945)Get code to link to this report
Tama in the storm

On behalf of Takahashi-san whose presence and help today was crucial !!

Participants: Takahashi, Marc, Yuhang, Manuel

Today from around 15h there was a really strong storm in Mitaka.

Issue 1: power shut down.

There was a power shut down (caused by a lightning) while we were doing experiment for few minutes.

We turned off everything but many parameters have to been checked as they have been reset. We didn't yet turn on laser or others electronic devices (We heard some strange sounds we need to investigate).

Takahashi-san was there to help with the compressed air leakage.

All the pumps were also turned off!

He closed the valves of the chambers and of the pipe.

When we arrived at the south end room it was quite hot and humid (similar situation as the other one). Takahashi-san turned the air conditioning on but this might show that it turned off by itself from time to time.

Issue 2: water in central room

Coming back from the end room we found out that a lot of water was leaking inside Tama on an electrical board (probably the general power).

We removed as much water as possible but this shows that there is a leak coming from there. The electric board seem not having any damages.

Issue 3: air conditioning in elec shop

Going inside the electrical shop we saw that one air conditioning system has fallen off the wall. The humidity didn't drain outside so a lot of water was on the floor. We removed 4 buckets of water.

Isse 4: air leakage

Takahashi-san also had the time to fix the air leakage by tightening the joints (without replacing them). When we were there, also other 2 joints in the central room started leaking air. We tightened them as well.

 

Finally, electricity seems to be back everywhere.

A careful check will be made tomorrow.

Takahashi-san said he will turn on the pumps / open the valves tomorrow.

R&D (FilterCavity)
Print this report.
MarcEisenmann - 18:51, Monday 13 August 2018 (944)Get code to link to this report
Toward the OPO

This entry will summarize past working days (sorry for the delay)

New Optical scheme and wiki sections :

The new optical scheme (v 31) ".svg" has been updated in the wiki. The ".png" is attached to this entry.

The available lenses have also been added to the "Optics" section of the wiki.

EOM alignment and p-pol power :

The 2 steerings mirrors before the EOM have been remplaced by PBSW-1064 which should only transmitt 5% of p-pol each.

When doing this, we saw that the lens before the EOM was a bit tilted so we aligned this EOM path again.

We now have

before EOM 10.0 mW
after EOM 8.7mW
p-pol after EOM 100 um

Note that the power values where chosen to compute easily the % transmission.. We can increase a bit the power if needed. However to lock the OPO, it is planned to use a similar photodiode to the one used to lock the FC where the power is ~200 uW.

It seems that p-pol inside a modulator can lead to amplitude fluctuations. Is this power low enough to avoid them or should install an additional PBS before the EOM?

P-Pol and CC beam characterizations :

In order to characterize this 2 beams, we did as for the FC green reflection.

We added one f=100mm lens and check the beam profiles after it.

This 2 characterizations are attached to this entry.

The lens after the EOM was then moved a little in order to match more precisely the beam waists.

The 2 beams were aligned before the first sterring mirrors of the OPO telescope using 2 irises and checking the power transmitted.

The 2 beams are now quite well overlapped on the rail as we can see on the beam profiler.

OPO telescope :

Using the CC beam as our reference, we designed a telescope that is now placed between the 2 last steering mirrors before the OPO on a rail.

Our first simulation didn't match the data. It seems that we need to understand it a bit better. Please note that the value of the FC relfected green beam parameter before the lens is wrong!

Using Jammt for the moment we could recover the beam parameters before the lens and design the telescope.

It consists of 2 lenses as attached to this entry (sol2).

Before the storm we found a mean beam waist of 36.3 um quite close to the nominal one!

A better characterization of the 2 beams will be performed tomorrow.

Images attached to this report
944_20180813105232_v31.png 944_20180813113830_ccbeamcharac.png 944_20180813113836_ppolbeamcharac.png 944_20180813114123_sol2.png 944_20180813114401_ccaftertelescope.png
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 20:13, Friday 10 August 2018 (943)Get code to link to this report
1310nm probe noise investigation

The noise may come from the fiber.
I checked with a sound generator on my phone and put the speaker near the fiber. I see the peak at 4690Hz (random choice, but the same thing happen for other frequencies) on the spectrum (see pictures). Some acoustic noise is coupled to the fiber. So I fixed the fiber with some tape.

I put the OD2 filter to reduce the power, then a non-polarizing BS to send half of the beam on the in-loop PD.
I put the in-loop PD on a separate optical board standing on a periscope post because there was no space on the breadboard.
Before the in-loop PD, I put a f=50mm lens. The in-loop PD is mounted on an XY lens mount for a fine centering of the beam on the detector.
I put the out-of-loop PD on the translation stage and moves it to center the beam inside the PD.

Both PDs have a load of 7.5kOhm.
On the oscilloscope, the two signals (AC coupling) are very similar. Also, the coherence is high.
I closed the loop but the noise doesn't reduce on the out-of-loop PD.

I took the spectra with 400 peakhold averages, not linear averages, because I'm interested in reducing the nose peaks, the spikes due to the jumps.
I really need to understand where these "jumps" come from.

Images attached to this report
943_20180810131035_acousticnoisefiber.png 943_20180810131049_25.jpg 943_20180810131139_20180810inloopoutofloop.png
Non-image files attached to this report
KAGRA MIR (Absorption)
Print this report.
ManuelMarchio - 15:21, Friday 10 August 2018 (942)Get code to link to this report
Comment to Preliminar design of the pump size reduction (Click here to view original report: 939)

I made a measurement of the pump beam profile to make sure of the parameters without the last converging lens.
Result:
waist = 500um
waist position = -1m

the axis origin is the converging lens mount.

Then I updated the Jammt design using these parameters for the initial beam.
The current converging lens is f=150mm, so Jammt gives a resulting waist of 67um at 165mm from the lens. See figure. 

I also made a measurement and fit after putting back the lens. the fit gives a waist of 70um at 171mm. Quite comparable with the jammt result.

then I updated the configuration to have a pump size of 70 - 75um (diameter).
See the diagram.

I need a diverging lens f=-125mm and a converging lens f=100mm

Images attached to this comment
942_20180810042456_pumpprofile.png 942_20180810070444_pumpprofile150mm.png 942_20180810081915_reducepumpsizev2.png